Redwood City, CA · 2026 Guide
    New 2025: 30-day permit fast-track via AB 1332

    Redwood City ADU
    Design & Permits

    Everything you need to build an ADU in Redwood City — lot eligibility, size limits, the eTRAKiT permit process, free GLADUR plans explained, and a full cost breakdown. All sourced from official City records.

    Max detached size
    Up to 1,200 sqft
    Setbacks
    4 ft rear & side
    Pre-approved review
    30 days (AB 1332)
    Parking required
    None — prohibited by law

    Data verified 2026-07-09 · City of Redwood City · Municode Zoning Article 37 · CA HCD

    Lot Eligibility

    Can I Build an ADU on My Redwood City Property?

    ADUs are permitted on most residential lots in Redwood City under California state law. Select your ADU type and zone below — results use verified City rules.

    Check My Lot

    Instant eligibility check — Redwood City rules as of 2026-07-09

    Eligible Zones

    ADUs are allowed in R-1, R-2, R-3 zones. No minimum lot size. State law requires ADUs anywhere single- or multi-family housing is permitted.

    No Owner-Occupancy Required

    California removed the owner-occupancy requirement in January 2020 (SB 13). You can build an ADU on a rental or investment property in Redwood City.

    Hillside Parcels — Verify First

    Some hillside parcels (e.g. Emerald Hills-adjacent neighborhoods) may require environmental or geotechnical review — verify per parcel with City Planning before finalizing design Contact City Planning at (650) 780-7234 before finalizing your design.

    ADU Types & Sizes

    What Can I Build on My Redwood City Lot?

    Redwood City allows four ADU types. Sizes are governed by Zoning Code Article 37 with a state-law floor of 800 sqft the city cannot go below.

    Most popular

    Detached ADU

    Max Size
    Up to 1,200 sqft
    Setbacks
    4 ft rear & side
    Height
    16 ft (25 ft two-story)

    Attached ADU

    Max Size
    Up to 50% of primary sqft (max 1,200 sqft)
    Setbacks
    Matches primary structure
    Height
    Matches primary structure
    Fastest path

    JADU

    Max Size
    Up to 500 sqft
    Setbacks
    Within existing structure — none
    Height
    Existing structure
    Budget-friendly

    Garage Conversion

    Max Size
    Existing garage footprint
    Setbacks
    Waived — existing legal structure
    Height
    Existing structure — waived
    Max detached ADU size
    1,200 sqft
    CA state max, adopted locally
    Height — new detached ADU
    16 ft (25 ft two-story)
    CA SB 897 (2022)
    Side & rear setback (detached)
    4 ft minimum
    CA Gov. Code §66332
    Setback for conversions
    Waived entirely
    CA Gov. Code §66332
    Parking required
    None
    CA Gov. Code §66333
    Minimum lot size
    None required
    CA Gov. Code §66310
    Owner-occupancy required
    No
    CA SB 13 (2020)
    State approval clock
    60 days (ministerial)
    CA Gov. Code §66333

    Permit Process

    How to Get an ADU Permit in Redwood City

    Permits are submitted online through eTRAKiT . Standard review runs 3–8 weeks; the new AB 1332 pre-approved plan fast-track targets 30 days for qualifying plan sets.

    AB 1332 Fast-Track — New 2025

    Redwood City is implementing California's AB 1332 pre-approved ADU plan program. Qualifying plan sets — including free HEART/GLADUR plans — target a 30-day review. Site-specific engineering and a complete permit package still required.

    #1: Incomplete plan set at intake

    Missing sheets, incorrect file naming, or absent Title 24 CF1R triggers rejection at intake before plan review even begins.

    #2: Utility capacity unresolved

    Water/sewer capacity confirmation from RCSMD or CalWater is commonly required before permit issuance — order it before submitting plans.

    1. 01

      Feasibility & Zone Verification

      Confirm your zone (R-1, R-2, R-3), setbacks, lot coverage, and any hillside or environmental overlays. Emerald Hills-adjacent parcels may carry additional geotechnical review — verify parcel-by-parcel with City Planning at (650) 780-7234.

    2. 02

      Evaluate Free Plans vs Custom Design

      HEART Housing / GLADUR offer free pre-reviewed ADU plans that qualify for the City's 30-day AB 1332 fast-track. zHeight evaluates whether a free plan fits your lot's setbacks, soil conditions, and utilities — or whether a custom design is the faster, safer path.

    3. 03

      Design & Engineering

      Full permit-ready plan set: architectural drawings, structural calculations, and Title 24 CF1R energy compliance — prepared to Redwood City standards and eTRAKiT file naming conventions.

    4. 04

      Submit via eTRAKiT

      Open your permit application on eTRAKiT (https://permits.redwoodcity.org/etrakit) and upload your plan set online. No city office visit required. zHeight handles the submission and monitors the portal for review status updates.

      Order water/sewer capacity confirmation from RCSMD or CalWater before submitting — commonly required before permit issuance.

    5. 05

      Plan Review & Corrections

      Standard review: 3–8 weeks. Pre-approved AB 1332 plans: 30-day target (new 2025). zHeight responds to all City correction letters until your permit is approved.

    6. 06

      Permit Issued — Build

      Pay permit fees to Redwood City online, receive your building permit, and schedule required inspections (foundation, framing, rough MEP, insulation, final) through the Building Division at (650) 780-7350.

    Cost Guide

    How Much Does an ADU Cost in Redwood City?

    ADU costs break into three buckets. City permit fees are valuation-based — verify current amounts with Planning before budgeting. Ranges below are Bay Area market estimates.

    Design & Engineering

    $7,000 – $16,000+

    zHeight flat-fee or custom quote. Includes architectural plans, structural calculations, and Title 24 CF1R. Hillside parcels requiring geotechnical coordination are at the higher end.

    City Permit Fees

    Valuation-based

    Minimum $125. Plan check: 65% of permit fee (building/MEP/fire) or 25% (electrical). Full tiered schedule in the City's Master Fee Schedule PDF — call (650) 780-7234 for current amounts before budgeting.

    Construction

    $300 – $500+ / sqft

    Paid to your licensed general contractor — not zHeight. Detached ADUs typically run $200K–$500K+ total. Conversions cost less; utility upgrades add cost. Get contractor bids after permit approval.

    Verify Permit Fees Before Budgeting

    The City of Redwood City uses a valuation-based fee table. The minimum permit fee is $125. Plan check fees are 65% of permit fee (min $125) for building, mechanical, plumbing, and fire; 25% of permit fee (min $125) for electrical. Full tiered amounts are in the City's Master Fee Schedule PDF — call Planning at (650) 780-7234 for current figures before you finalize your budget.

    Want a cost estimate for your specific lot and ADU type?

    Get a Free Project Estimate

    Why zHeight

    Free GLADUR Plans vs. a Complete Permit Package

    The City's AB 1332 program and HEART Housing / GLADUR's free ADU drawings are a genuine head start. Here's exactly what they include — and what still requires site-specific work before eTRAKiT will accept your submission.

    Free plans are a real option. Free pre-reviewed detached ADU construction plans (studio through larger units) funded by BAAQMD grant. These qualify for the 30-day fast-track. If a free plan fits your lot, zHeight can assemble the site-specific permit package around it — adding structural engineering, Title 24 CF1R, and eTRAKiT submission — rather than starting from scratch.

    What you needFree GLADUR PlanszHeight Package
    Plan drawingsGeneric templates reviewed for a typical lotDrawn specifically for your lot, setbacks, and configuration
    Structural engineeringGeneric calcs — may not match your soil or foundationSite-specific structural calcs stamped by a licensed engineer
    Title 24 CF1RNot included — required separately before permit is issuedIncluded in every permit package
    eTRAKiT submissionYou submit and monitor yourselfzHeight handles submission and portal monitoring
    Plan check correctionsYou respond to City correction letterszHeight responds to all corrections until permit is issued
    Hillside / overlay reviewNot addressed in generic plansFlagged in feasibility and addressed in design

    Speed through complete first submissions

    The #1 cause of permit delays is an incomplete plan set at intake. zHeight's organized, City-compliant submission — correct file naming, all required sheets, Title 24 CF1R included — avoids rejection before review even begins.

    Design & permitting only — not the builder

    zHeight provides architectural drawings, structural engineering, Title 24 compliance, and permit processing. We coordinate with your chosen licensed General Contractor throughout — we do not perform construction or contracting.

    FAQ

    Redwood City ADU Questions, Answered

    Common questions about ADU eligibility, zoning, setbacks, the eTRAKiT portal, GLADUR plans, and costs in Redwood City.

    Have a question not answered here?

    Our Redwood City ADU experts typically respond within one business day.

    Our Services

    Design, Planning & Permitting — Not Just ADUs

    From a kitchen remodel to a full ADU build, zHeight handles the design, planning, and permitting. We work alongside your contractor — we are not the builder.

    Design & permitting only. zHeight provides architectural drawings, structural engineering, Title 24 compliance, and permit processing. We do not provide construction or contracting services. We coordinate with your chosen builder throughout the process.

    zHeight — Redwood City

    Ready to Build Your Redwood City ADU?

    We handle the complete permit package — architectural drawings, structural, Title 24 CF1R, eTRAKiT submission, and correction response — so your project moves from submission to permit.

    All regulatory data verified 2026-07-09 against City of Redwood City ADU Ordinance, Zoning Code Article 37 (library.municode.com/ca/redwood_city), City Master Fee Schedule, CA Gov. Code §66310–66342, and CA AB 1332 (2023). Fee amounts beyond the stated minimums should be confirmed with City Planning at (650) 780-7234 before budgeting.